Nearly 400-meter overpass between Kamennaya Horka and Lebyazhy promised to open by the end of the year
The bridge crossing over the railway will directly connect the capital's Frunzenski and Tsentralny districts and allow drivers to avoid detouring via the MKAD. Construction has already reached its final stage; however, before opening to traffic, the structure still faces rigorous testing.

The current stage of construction is reported by the "Minsk-Novosti" agency. According to Siarhei Rubchenia, director of the general contractor—Bridge Construction Directorate (MBU) No. 2 of "Mostobud"—the overall completion of the project stands at about 95%, although in the middle of summer it had not even reached half.
The length of the structure is 381 meters. It features 13 spans, on which all 224 reinforced concrete beams have already been installed. With the exception of one short 18-meter span, the remaining spans use beams 33 meters in length and weighing over 60 tons each. The piers have already been fully erected, the beam decks have been laid, and more than half of the bridge deck, which will include a concrete leveling layer and a protective asphalt concrete layer, has been paved.

Bridge builders are currently working on the upper sections of the flyover: laying asphalt concrete mix and paving slabs, waterproofing the roadway, and installing railing barriers and lighting poles. Of the 24 planned poles, only five remain to be installed. Asphalt has already been laid and road markings applied on a portion of the crossing.


According to Siarhei Rubchenia, all monolithic concrete work on the site will be completed by the end of November, followed by asphalt paving. However, traffic will not be allowed onto the flyover immediately after that: first, all necessary permits must be obtained, special sensors installed, and tests conducted using multi-ton heavy machinery. This inspection is planned for the first half of December in order to open traffic by the end of 2026.

Around 120 people are employed in the construction, working around the clock, with no days off or holidays. On peak days, the number of workers on site reached 160. In addition to primary installation, they carry out the full range of related work, including finishing and painting the structures.

Preparing the construction site took a lot of time due to the large number of utility networks running within the construction boundary and crossing at various levels. Before beginning the erection of the piers, the contractor had to obtain permits from operating organizations, procure materials, excavate soil, install new utilities, and backfill them. As a result, the project encompassed not only the flyover itself, but also the reconfiguration of storm drains, heating mains, water supply lines, railway catenary lines, and landscaping of the surrounding area.
The most critical stage was crossing the overpass directly over the railway. As Siarhei Rubchenia explained, for daytime and nighttime work, the builders were granted "windows" of only two hours each, with these windows scheduled well in advance—70 days before the start of installation.

New exits and continuation of the third ring road
Simultaneously with the flyover's construction, the adjacent street and road network was reconstructed. The bridge itself features three traffic lanes in each direction. From the direction of Tsimirazeva Street, drivers will be able to exit the overpass and turn either left—towards the MKAD, or right—towards the city center. From the direction of Kalesnikava Street, the scope of work was smaller: there, the exit ramp was connected to the existing road network and traffic lights were installed at the nearest intersection.
This flyover will become the first connecting link of the third transport ring of Minsk and is expected to relieve city streets along with the MKAD. The next step should be the construction of the ring's second link—another flyover over the railway that will connect Karzhaneuski and Churlyonis streets. Bridge Construction Directorate No. 2 of "Mostobud" has already stated that they are ready to take on this project as well.
Now reading
“Almost everyone voted against me.” The creator of the “Bykhaw Madonna” was expelled from the Union of Artists on the orders of mocked local authorities
Comments